Updated notice of temporary traffic lights and closure of Rugby Road, Cubbington
Work item: HS2-BBV-25-1248
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Cubbington
- Worksite Name
- Rugby Road
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 29/09/2025
- Estimated End Date
- 22/11/2025
What we are doing
We recently updated you on works to Rugby Road Overbridge and the permanent road realignment to start on Monday 15 September 2025. These works will now start on Monday 29 September 2025. We require a series of phased traffic management to safely undertake earthworks, utility and highway works.
Phase one: Monday 29 September to Friday 3 October 2025
Two-way temporary traffic lights will be in place 24/7.
Phase two: Monday 6 October to Saturday 1 November 2025. Full road closure will be in place 24/7.
Phase three: Saturday 1 November to Saturday 22 November 2025.
Three-way temporary traffic lights will be in place 24/7.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]