Notice of temporary traffic lights and closure of Rugby Road, Cubbington

Work item: HS2-BBV-25-1248

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Cubbington
Worksite Name
Rugby Road
Contractor
BBV JV
Type of works
Traffic management
Estimated Start Date
15/09/2025
Estimated End Date
22/11/2025

What we are doing

As we continue to progress works on Rugby Road Overbridge and the permanent road realignment, we require a series of phased traffic management to undertake earthworks, utility and highway works.

Phase one:

Monday 15 September to Friday 19 September 2025 Two-way temporary traffic lights will be in place 24/7.

Phase two:

Monday 6 October to Saturday 1 November 2025. Full road closure will be in place 24/7.

Phase three:

Saturday 1 November to Saturday 22 November 2025. Three-way temporary traffic lights will be in place 24/7.

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]