Notice of temporary traffic lights and closure of Rugby Road, Cubbington
Work item: HS2-BBV-25-1248
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Cubbington
- Worksite Name
- Rugby Road
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 15/09/2025
- Estimated End Date
- 22/11/2025
What we are doing
As we continue to progress works on Rugby Road Overbridge and the permanent road realignment, we require a series of phased traffic management to undertake earthworks, utility and highway works.
Phase one:
Monday 15 September to Friday 19 September 2025 Two-way temporary traffic lights will be in place 24/7.
Phase two:
Monday 6 October to Saturday 1 November 2025. Full road closure will be in place 24/7.
Phase three:
Saturday 1 November to Saturday 22 November 2025. Three-way temporary traffic lights will be in place 24/7.
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]