What we are doing

From 15 April to 29 May, between 8am to 6pm, we will be carrying out works on Brunswick Road.

From 22 April, we will reinstall a road closure on Brunswick Road and start works to protect the gas mains below the road. We have changed the diversion route following a review of the traffic numbers. You can view a map of the new diversion route on page two. This has been agreed with Ealing Council

 

 