Public Rights of Way Closures, Great Missenden
Work item: 1MC12-EKF-ER-NTE-CS03-000001
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Great Missenden
- Contractor
- EKFB JV
- Type of works
- Footpath closures
- Estimated Start Date
- 26/04/2021
- Estimated End Date
- 01/10/2026
What we are doing
As we have progressed our works, we have needed to close some footpaths in the areas around Great Missenden, Wendover Dean and The Lee so that works can be carried out safely.
The attached document shows the closures, durations, and which footpaths have been kept open to still allow for connectivity.
Below are the footpath locations and intended dates of when the closures will be in place:
• WEN38/1 and TLE/2 – 17th April 2021 – Autumn 2026
• TLE/5 – 22nd April 2021 – Autumn 2026
• WEN/36/2 – 1st May 2021 – Autumn 2026
• GMI/12 and GMI/13 – 30th May 2021 – Autumn 2026
• WEN39/1, WEN39/2 and WEN40 – March to Autumn 2026
• WEN37/1 & TLE/3 (Bowood Lane) – To remain open with a diversion
• GMI/2 – To remain open with a diversion
The footpaths that we are closing will have notices and signposted local diversions in place where necessary. Where diversions are in place there will be some marshalled crossing points when they cross our works area to ensure the safety of all footpath users.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]