Works to west retaining wall in front of Cartmel and Coniston until summer 2024
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Site-1-26/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Cartmel, Regent's Park Estate
- Worksite Name
- Euston Throat
- Contractor
- SCS JV
- Type of works
- Construction, Excavation works, Piling
- Estimated Start Date
- 03/10/2023
- Estimated End Date
- 30/06/2024
What we are doing
Works to west retaining wall – autumn 2023 to summer 2024
We are currently constructing a large retaining wall in front of Regent’s Park Estate. This wall, which extends from Granby Terrace to Hampstead Road, will form the side of the new HS2 railway cutting.
From October 2023 we were working in sections between Cartmel towards Coniston, excavating a deep trench, using a high powered water blaster to roughen the top of the concrete piles and building the concrete slabs. This works to continue until summer 2024. Please see the link to September 2023 notice ‘Works next to Coniston and Cartmel – October 2023 to June 2024‘ below.
Weekend and extended hours work near Coniston and Cartmel – March
We are currently constructing a large retaining wall in front of Regent’s Park estate. This wall, which extends from Granby Terrace to Hampstead Road, will form the side of the new HS2 railway cutting.
We will complete a concrete pour on 28 March during our normal working hours. Ahead of this, we will carry out preparatory works to create the formwork into which the concrete will be poured. We will carry out these works on Saturdays in March from 8am to 5pm. You may notice periods of increased noise while we carry out this work. We will aim to complete noisy works between 8am and 1pm and monitor noise levels closely to ensure we are working within the approved limits.
We are sorry for any disruption this work might cause.
For further details of weekend and extended hours work please follow this link.
Download information relating to these works
- Noisy works in front of Cartmel and Coniston - 29 November to April 2024
- Works next to Coniston and Cartmel - October 2023 to June 2024
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]