Find all our HS2 information for motorway works in one place. This includes advanced notifications, diversion routes and further information.

M6 and M42 closures June to November

We will be carrying out a series of major engineering works over the M42 and M6 between June and November 2026. These works are required so that we can install three new railway structures for Britain’s new high-speed railway.  

Our next weekend closure to continue these works will be over the M42 from 24 to 27 July.  The closure will be between J6 to 9  northbound and J7a to 6 southbound.  There will also be temporary restrictions on the M6toll between M6 J3a to T1 northbound and at T2 southbound.   

Planned closure dates 

The current programme of weekend closures is scheduled as follows:

26–29 JuneFirst beam installation for the M42 twin-box structure
24–27 JulyWater Orton viaduct installation and continued M42 beam works
14–17 AugustContinued Water Orton and M42 installation works
21–24 AugustM6 South Viaduct West deck slide
18–21 SeptemberFinal M42 beam installation and viaduct works
October/NovemberWater Orton viaduct parapet installation

All dates remain subject to consent and operational requirements.

Alongside our works to install these new structures there will be additional motorway closures to facilitate: 

  • preparatory and  
  • ongoing works 

Details of these closures can be found here:  

DatesWorksAdditional information
13 to 18 JulyM42 J7a northbound link to M6 southboundFind out more
3 to 4 AugustM42 M6 Link Road & M42 northbound
17 to 18 AugustM42 northbound, junctions 5a to 9
22 to 23 OctoberM6 junctions 4/4a in both directions and loop including slip roads
24 to 25 OctoberM42 junction 7 link to M6

Find out more

We will be holding a series of community information events in collaboration with National Highways to help residents, businesses and commuters understand the works and prepare for the closures.  

These events will provide:  

  • Details of planned motorway closures  
  • Information on diversion routes  
  • Opportunities to ask questions and speak with the teams  
  • Updates on the project   
DateVenueTimes
Wednesday 8 JulyMartson Green Village Hall2pm until 6pm
Thursday 9 JulyBalsall Common2pm until 6pm
Thursday 9 JulyBirmingham Business Park11.30am until 2pm
Tuesday 14 JulyWebinar1pm to 2pm
Tuesday 14 JulyChelmsley Wood Three Trees10am until 2pm
Thursday 16 JulyChelmsley Wood Onward Club4pm until 8pm
Thursday 16 JulyAldi ColeshillTBC
Saturday 18 JulyDordon Village Hall10am until 2pm
Tuesday 21 JulyM42 motorway closure webinar   1pm until 2pm

 

For details visit our Events webpage

Plan ahead before you travel

Plan ahead before you travel

You will still be able to reach your destination. Please follow the fully signed diversion and allow extra time for you journey.

For real-time updates on roadworks and closures, including HS2 activities on public highways, visit one.network.

Our works

M42 twin-box structure

Once complete, the 300-metre-long M42 twin-box structure will allow trains to travel above the motorway while vehicles continue through the box below.  

Engineers will install 175 individual beams weighing between 56 and 92 tonnes across four weekend closures.  

The structure has been designed using modular construction techniques, allowing much of the work to be completed without closing the motorway.  

Water Orton viaduct installation 

In nearby Water Orton, engineers are preparing to extend two viaducts that will carry high-speed trains towards Birmingham Curzon Street and the Washwood Heath rolling stock depot.  

Rather than building the final sections using traditional cantilever methods, the remaining viaduct spans will be assembled beside the motorway and moved into place using self-propelled modular transporters.  

This innovative approach significantly reduces installation time and minimises disruption for motorists.  

Works are scheduled to begin on Friday 24 July 2026.  

M6 South Viaduct West 

The final major operation involves installation of the M6 South Viaduct West near Chelmsley Wood.  

Using a fully restrained deck-slide process, engineers will move the viaduct into position while keeping traffic moving during key phases of the operation.   