Copthall tunnel
Tunnel construction
To build the tunnel, the site team dug 30 metres down from ground level. Piles were installed at the portal to support the shallower tunnel sections.
The tunnel uses a reinforced concrete structure forming a base slab, walls, and roof. The box structure is formed with tied steel bars encased in concrete – designed for high-speed trains and to support the green landscaping above.
To construct the roof, a 40-metre-long temporary deck is positioned between the box walls, to support it during concrete pouring. The deck is moved 20 metres forward, so the next roof section can be built.
Harvil Road, near the tunnel, has been realigned to pass over the western end of Copthall tunnel. The road realignment deck was installed and reopened in February 2024.
Email newsletters
Subscribe to our Project Update newsletter to receive the latest news and updates about HS2.




