Skip to main page content

Work items found 4700

A list of current and past work items for the HS2 project.
Name Status Location Estimated Start Date Estimated End Date
A452 Kenilworth Road -roundabout construction Completed

Berkswell

20/07/2021

21/07/2021

Water supplies in your area Completed

Old Oak

12/07/2021

16/07/2021

Changes to traffic rerouting around Northway Island from Monday 19 July to late August 2021 Completed

Bickenhill, Marston Green

19/07/2021

22/08/2021

Notification of ground investigation survey work- Whitmore Wood Completed

Whitmore

09/09/2021

28/10/2021

Ongoing monitoring in and around the Euston Approaches Completed

Camden, Delancey Street, Hampstead Road, Mornington Terrace, Park Village East, Parkway

15/07/2021

27/09/2021

Notice of ecology works, Southam Completed

Ladbroke, Southam

05/07/2021

31/07/2021

Notice of Utility Works at Curzon Street, Birmingham Completed

Birmingham

12/07/2021

12/12/2021

Borehole install behind 119 and 121 Parkway Completed

Parkway

12/07/2021

16/07/2021

Notice of increased vehicle movements during extended working hours Completed

Old Oak

01/07/2021

31/07/2021

Notice of Installation of site office at Mandeville Road vent shaft site Completed

Northolt

12/07/2021

14/07/2021

Update- Notice of traffic management Welsh Road, Offchurch Completed

Offchurch

28/06/2021

24/07/2021

Notice of utility surveys – Curzon Street Completed

Birmingham

09/07/2021

09/07/2021

Notice of topographic surveys –Saltley Viaduct Completed

Saltley

12/07/2021

16/07/2021

Notification of trial holes at M42 junction 7 and 7A Completed

Coleshill

12/07/2021

15/07/2021

Notice of main construction works – Curdworth Completed

Curdworth, Lea Marston

05/07/2021

05/11/2021

Temporary closure of the layby, A5 Hints area Completed

Hints

05/07/2021

09/07/2021

A515 Lichfield Road, temporary lane closures and satellite compound set up Completed

Kings Bromley

12/07/2021

27/08/2021

Topographic surveys – Watling Street, Rockhill area Completed

Hints

05/07/2021

09/07/2021

Update: Next phases of utility works in Victoria Road Completed

Victoria Road

30/06/2021

31/01/2022

Traffic management on the A446 near Coleshill Completed

Coleshill

05/07/2021

16/07/2021