24/7 works over holiday period in Euston Approaches – 24 to 28 & 31 December

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-09/12/2022

Work Item Summary

Project Phase
Phase 1
Location
Euston Approaches
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Bridge inspections, Extended working hours, Monitoring equipment, Survey
Estimated Start Date
24/12/2022
Estimated End Date
31/12/2022

What we are doing

We plan our construction activities to avoid working over the holiday period wherever possible however for safety, we can only carry out these works when the tracks are not in use. From 24 to 28 & 31 December, we will carry out works onsite next to the railway.  We will work 24/7 to complete the works before the tracks reopen.

  • Piling preparation works at track level in Camden Cutting North, in the section of our worksite just south of Parkway.
  • Ongoing monitoring of the bridges and structures at track-level within Euston Approaches including surveys to investigate the ground underneath Mornington Street bridge.

For further details please see notification below.

Please be aware that the current traffic management on Mornington Street Bridge and Hampstead Road/Harrington Square will remain in place over Christmas period, for further details follow the links below:

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]