24-hour works over bank holiday weekend in Euston Approaches
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-08/08/2024
Work Item Summary
- Project Phase
- Phase 1
- Location
- Camden Cutting north, Granby Terrace bridge, Hampstead Road
- Worksite Name
- Euston Approaches
- Contractor
- SCS JV
- Type of works
- 24 hour working
- Estimated Start Date
- 24/08/2024
- Estimated End Date
- 27/08/2024
What we are doing
24-hour works (day and night) over bank holiday weekend – 24 to 27 August
We plan our construction activities to avoid working over the holidays wherever possible but for safety, we can only carry out works next to the railway when the tracks are not in use. We will work 24 hours – day and night – over the long weekend, to complete works next to the tracks before they reopen.
The works will include:
- 24-hour works near Parkway Tunnels in Camden Cutting north – 24 to 27 August
- Weekend works at Granby Terrace bridge – 24 to 26 August, 8am to 8pm and 31 August to 1 September – 8am to 8pm
- Hoarding replacement within site – north of Granby Terrace bridge – 24 to 27 August, 8am to 8pm
- Hoarding maintenance on Hampstead Road – 24 to 25 August, overnight
We will carry out all noisy works during the day, and quieter works at night. We will use acoustic blankets to limit noise and will monitor noise levels closely to ensure we are working within the approved limits.
For further details of above works, please follow the link to the notification below.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]