Update notice of works along Old Oak Common Lane
Work item: HS2-MW-BBVS-Ph1-OOC-So-S1-prog-works-9-22/05/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak, Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Construction, Ground investigations
- Estimated Start Date
- 10/02/2023
- Estimated End Date
- 23/07/2023
What we are doing
High Speed Two (HS2) is the new high speed railway for Britain
We wrote to you in February 2023, about the works taking place along Old Oak Common Lane, including the current lane closure. This update outlines the next phase of work that is coming up along Old Oak Common Lane.
Trial hole investigations on Old Oak Common Lane northbound – until 23 July
As part of our ongoing programme of works, we are currently undertaking trial hole investigations on the northbound lane and footpath on Old Oak Common Lane, be between Kildun Court and the existing substation. The work are now expected to finish on 23 July. Work will take place, between our core working hours of 8am and 6pm Monday to Friday.
Once this work is completed the area will be backfilled and the single lane and footpath closure will go back to the southbound lane. London Borough of Ealing will be resurfacing Old Oak Common Lane from 31 July to 2 August.
We will also be working on the south end of Old Oak Common Lane from 31 July, for approximately five weeks. These works will be carried out intermittently, the dates are subject to change and we will keep the local community informed.
For further details please see update notification below.
Download information relating to these works
- Update notice of works along Old Oak Common Lane - extended until 23 July
- Update notice of works along Old Oak Common Lane - 3 to 14 July
- Update notice of works along Old Oak Common Lane - 6 to 30 June
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]