West End Road bridge monitoring equipment installation

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-08/02/2023

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon, London
Location
West End Road
Worksite Name
West End Road, West Ruislip
Contractor
SCS JV
Type of works
Monitoring equipment
Estimated Start Date
27/02/2023
Estimated End Date
02/03/2023

What we are doing

In advance of tunnelling works nearby, it is necessary to monitor the West End Road bridge. Starting on 27 February until 2 March, we will be installing monitoring prisms on the underside of the railway bridge near to the Bedford Road junction. As the prisms need to be installed at height, we will use a ‘cherry picker’ (mobile elevated working platform) within the work areas shown on the map overleaf. We will be using a small drill to make a hole and then a hammer to knock the monitoring prism in place. Any noise will be minimal and very brief.

How these works might affect you

Temporary traffic management and pedestrian crossings will be in place to ensure that we carry out the works safely. We would like to apologise in advance for the disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.