Utilities works on Masons Green Lane
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-1-22/08/23
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- A40
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 04/09/2023
- Estimated End Date
- 16/09/2023
What we are doing
From 4 September to 9 September 2023 (phase one) and 11 September to 16 September 2023 (phase two) we will be carrying out two ground investigations on Masons Green Lane.
The ground investigations will take place between 8am to 6pm Monday to Friday and 8am to 1pm Saturdays, if required. We will use noise reducing barriers where possible to help minimise any noise disruption to the local community, working as efficiently as possible whilst keeping our work areas safe and tidy.
The ground investigations will consist of digging a temporary trench to confirm the location of utilities under the surface of the road. The investigations will help us to understand and aid the design of the new railway and the best ways to protect or divert any utilities during construction.