Notice of temporary traffic lights on Uttoxeter Road, Blithbury
Work item: HS2-EW-BB-Ph2A-Prog-works-38-24/08/2023
Work Item Summary
- Project Phase
- Phase 2a
- Region
- Staffordshire
- Location
- B5014, Uttoxeter Road
- Worksite Name
- B5014, Uttoxeter Road
- Contractor
- Balfour Beatty
- Type of works
- Ecological surveys, Fencing
- Estimated Start Date
- 13/09/2023
- Estimated End Date
- 22/09/2023
What we are doing
As part of our early environmental works, we are undertaking ecological surveys and fencing works in areas off Uttoxeter Road. These works are required to demarcate and secure land under possession by HS2.
Balfour Beatty will be using flatbed road vehicles and trailers to deliver material as required to the working area.
We will need to install temporary two-way traffic lights on Uttoxeter Road at Blithbury, to manage the safe movement of the vehicles and people into the working areas.
We will put the traffic lights in place from Wednesday 13 September to Friday 22 September 2023 9am-5pm
Download information relating to these works