6 month lookahead of works at Old Oak Common

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-79-23/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Extended working hours
Estimated Start Date
13/12/2022
Estimated End Date
30/06/2023

What we are doing

Extended Working Hours
Following recent enquiries and feedback from residents, we are outlining the works that currently require extended working hours at Old Oak Common Station. We have permission from the local authorities (London Borough of Ealing / London Borough of Hammersmith and Fulham) to work outside of our core working hours of 8am – 6pm Monday – Friday, and 8am – 1pm on Saturdays for a few key work activities.

These works require us to work outside of our core working hours due to a range of reasons, including health and safety, permissions to work near the Network Rail boundary which is only available over night and concrete works.

The table below outlines the work activity, timescales of work and time we can work for each activity.

Please note that whilst these extended hours are in place, the work will not always take place everyday.

These allowances to work outside of core working hours have been made with strict conditions enforced by the local authorities and the site teams have been briefed to respect the local community when these works are taking place.

Each activity is outlined in detail in the attachment.