A38 overnight lane and slip road closures in Streethay
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-2-24/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Streethay
- Worksite Name
- A38
- Contractor
- BBV JV
- Type of works
- Construction, Traffic management
- Estimated Start Date
- 11/04/2022
- Estimated End Date
- 29/04/2022
What we are doing
We are constructing a bridge to take the A38 near Streethay over the HS2 line. During the parliamentary stages we identified ways to reduce the visual impact of the scheme, we responded to concerns and the design was changed to a cutting. This means the HS2 line will now run under the A38 and existing railway lines, so that it is less visible in your line of sight.
During this phase of work, we are constructing a new access point off the Streethay southbound slip road to allow us to undertake enabling works alongside the South Staffordshire line.
To carry out this phase of work safely, we will install single lane and overnight carriageway closures on the A38 southbound, inclusive of the slip road at Streethay from 9pm on Monday 11 April 2022 for three weeks.
• Week one (three nights): Monday 11 to Wednesday 13 April
• Week two (four nights): Tuesday 19 to Friday 22 April. The southbound carriageway closure will take place on Thursday 21 and Friday 22 April
• Week three (five nights): Monday 25 to Friday 29 April.
We will not have any closures during the Easter weekend. Our working hours during the overnight closures will commence at 9pm
each evening and the road will reopen at 5:30am each morning. We may be on site up to an hour before or after our working hours to set up and secure our equipment.
Our work is subject to consents.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]