A452 Kenilworth Road -roundabout works

Work item: HS2-EW-LM-Ph1-Ar-No-N1-Prog-works-17-07/03/2022

Work Item Summary

Project Phase
Phase 1
Region
Solihull, West Midlands
Location
A452
Worksite Name
Park Lane
Contractor
LM JV
Type of works
Road closure, Traffic management
Estimated Start Date
22/08/2022
Estimated End Date
04/09/2022

What we are doing

Please find below dates for traffic management to support the final phases of construction of the roundabout on the A452 Kenilworth Road, Berkswell, close to Park Lane.                                          

22 Aug to 26 Aug – lane 1 closures northbound and southbound 9.30am to 3.30pm (contingency dates 5 Sept to 7 Sept)

30 Aug to 2 Sept – lane 2 closures northbound and southbound 9.30am to 3.30pm (contingency dates 8 Sept to 9 Sept)

30 Aug pm to 1 Sept am – overnight full northbound road closure 8pm to 6am with diversion. Park Lane access will be under escort from the A452.

2 Sept pm to 4 Sept am – overnight full southbound road closure 8pm to 6am with diversion. Park Lane access will be under escort from the A452.

Traffic management, including all signage, will be erected as and when required subject to consent, site and weather conditions. Please keep an eye out for signage on the road as dates are also subject to change as indicated above. We are working closely with SMBC to minimise disruption.

Local diversions will be clearly signposted. Access for residents and businesses within the A452 closure will be maintained by approaching the traffic marshall at the relevant closure point. For live up-to-date traffic information and diversion routes please go to one.network.