A452 Kenilworth Road -surfacing works. Updated dates

Work item: HS2-EW-LM-Ph1-Ar-No-N1-Prog-works-3-16/11/2022

Work Item Summary

Project Phase
Phase 1
Region
Solihull, West Midlands
Location
Berkswell
Worksite Name
Park Lane
Contractor
LM JV
Type of works
Road closure
Estimated Start Date
09/01/2023
Estimated End Date
27/01/2023

What we are doing

Surfacing and planting work is required at the new roundabout scheme at Park Lane along the A452, Berkswell. To carry out these works safely, a lane closure will be in place along the A452 southbound from Monday 9 January to Friday 13 January and northbound Monday 16 January to Friday 20 January. There will be a full overnight closure of the northbound carriageway from 8pm on Wednesday 25 January to 6am on Thursday 26 January and 8pm on Thursday 26 January to 6am on Friday 27 January.

Please check signage on the road as dates may change. All work is subject to consent, site and weather conditions.

Diversions will be clearly signposted. Access for residents and businesses within the closure area will be maintained. For live up-to-date traffic information and diversion routes please go to one.network. Any changes will be published on the hs2insolihull website.