A515 Lichfield Road, temporary lane closures and satellite compound set up
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Prog-works-23-05/03/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Kings Bromley
- Contractor
- BBV JV
- Type of works
- Construction, Traffic management
- Estimated Start Date
- 12/07/2021
- Estimated End Date
- 27/08/2021
What we are doing
To maintain a safe area for construction staff, there will be a temporary lane closure controlled by 2 way traffic lights on the A515, Lichfield Road.
We will set up a working area, on a section of land in the Parish of Kings Bromley, on the A515, Lichfield Road. These works will be to prepare the access and set up for our satellite compound.