Abnormal load deliveries to North Portal site, Great Missenden, Buckinghamshire

Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Traf-05-07/02/2025

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Great Missenden
Worksite Name
North Portal
Contractor
Align JV
Type of works
Delivery of materials
Estimated Start Date
17/02/2025
Estimated End Date
15/09/2027

What we are doing

We are bringing plant and materials onto site that will be used to build GMI/2 and GMI/12 overbridges, and for our works in Leather Lane in South Heath, Great Missenden, Buckinghamshire. The equipment is large and will be brought to site on wide vehicles, some with police escort.

Through discussions between hauliers, local authorities, and police, it has been agreed that the route chosen is the safest and least impactful route available.

On various dates from mid-February 2025 to Summer 2027 at 11pm, the abnormal load vehicles will take the following route:

  • Exit the M25 at junction 16 to join the M40
  • Exit the M40 at junction 2 to join the A355 heading north
  • Exit the A355 at the A413 junction heading west
  • Travel along the A413 to the North Portal site entrance at Link Road, Great Missenden.

For further details and the map of abnormal loads route please see notification below.