Advance Notice for planned utility works on A40 Western Avenue
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-2-21/06/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Hanger Lane, Western Avenue
- Worksite Name
- Utilities
- Contractor
- SCS JV
- Type of works
- Gas Main Works
- Estimated Start Date
- 27/06/2023
- Estimated End Date
- 07/10/2023
What we are doing
INFORMATION EVENT IN JULY 2023
We are holding an online information event about these works on 6 July 2023 from 6:30pm to 8pm
At this event you will be able to ask questions and find out more about:
- what this means for you in your local area
- temporary changes to the road network (A40 Western Avenue) and;
- measure we will have in place to reduce disruption
You will be able to speak with our local engagement and utilities team.
We will be running this event via Microsoft Teams.