Amersham site, tower crane removal
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Prog-works-07-12/07/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413
- Contractor
- Align JV
- Type of works
- Decommissioning works
- Estimated Start Date
- 10/08/2024
- Estimated End Date
- 11/08/2024
What we are doing
We will begin to dismantle and remove the tower crane at our Amersham vent shaft site from 5:30am on Saturday 10 August 2024.
This crane was used to construct the vent shaft and is no longer needed on site. Works will continue across the weekend and are expected to be finished by 8pm on Sunday 11 August.
To carry out the removal of the crane safely, a full road closure of Whielden Lane between Whielden Street and A404 will be implemented.
Access to Amersham hospital for all vehicles will be via Whielden Street only during the closure. Buses will also be diverted route for the duration of these works. Pedestrian access will be maintained along Whielden Lane and will be facilitated by traffic marshals.