Update: Works at Canterbury Works site over Easter

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-2-26/03/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Camden
Location
Canterbury Works
Worksite Name
Canterbury Works
Contractor
SCS JV
Type of works
Worksite / compound set-up
Estimated Start Date
29/03/2024
Estimated End Date
01/04/2024

What we are doing

Work activities over the Easter weekend

The majority of our scheduled works at the Canterbury Works Ventilation Shaft and Headhouse site will stop for the duration of the Easter weekend.

There will be minimal works taking place on Good Friday, 29 March. This will mainly consist of jet washing within the shaft. This work should not be impactful to our neighbours.

The overnight works will finish at 7am on Friday 29 March and will not restart until Tuesday 2 April.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]