B4114 Birmingham Road, Coleshill
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-17-13/11/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Coleshill
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 08/01/2024
- Estimated End Date
- 04/02/2024
What we are doing
We are continuing to prepare for works to construct the Coleshill Viaducts that will carry the HS2 railway over the existing B4114 Birmingham Road. As part of this, we will complete works to tie in a new temporary road realignment for the B4114 Birmingham Road. This realignment will remain in place for the duration of the viaduct works.
To complete the works safely, we will install a four-week closure. The closure will be in place from Monday 8 January until Sunday 4 February, 24 hours a day, seven days a week.
Access to pedestrians, cyclists, businesses and residents will be maintained throughout the works and a clear diversion route will be in place at all times.