Borehole install behind 119 and 121 Parkway
Work item: HS2-EW-SCS-Ph1-Ca-S1-Prog-works-4-21/06/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Parkway
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 12/07/2021
- Estimated End Date
- 16/07/2021
What we are doing
Update: Please be aware that borehole install works planned to be carried out from 12 to 16 July were delayed until further notice.
Borehole install behind 119 and 121 Parkway
- A new borehole will be installed in the car park area behind 119 -121 Parkway (in front of the gates to 117 Parkway)
- This borehole to monitor the level of ground water in this area, helping us to plan and monitor the impact of our works.
- The car park area behind 119 -121 Parkway will be closed and parking in this area will be temporarily suspended for the duration of work.
- Access to properties will be maintained at all times.
- Acoustic blankets in place to limit noise and dust.
For further details please see the notification below.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]