Breakspear Road South closure, 1 to 16 April

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Traf-1-16/03/2023

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon, London
Location
Breakspear Road South
Contractor
SCS JV
Type of works
Bridge protection works, Utility works / surveys
Estimated Start Date
01/04/2023
Estimated End Date
16/04/2023

What we are doing

From 1 to 16 April 2023, we will be carrying out works along Breakspear Road South, north and south of the Network Rail
bridge. For safety reasons, a road closure will be in place for the duration of these works. These works include:

  • Network Rail carrying out repair works on the bridge, structural examinations and vegetation works
  • HS2/SCS installing utilities trenches to allow for the connection of a water supply for the tunnel boring
    machines
  • HS2/SCS carrying out patch repairs to potholes around the
    Chiltern Bridge and HS2 site entrance

Access will be maintained for residents.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]