Breakspear Road South closure, 1 to 16 April

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Traf-1-16/03/2023

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon, London
Location
Breakspear Road South
Contractor
SCS JV
Type of works
Bridge protection works, Utility works / surveys
Estimated Start Date
01/04/2023
Estimated End Date
16/04/2023

What we are doing

From 1 to 16 April 2023, we will be carrying out works along Breakspear Road South, north and south of the Network Rail
bridge. For safety reasons, a road closure will be in place for the duration of these works. These works include:

  • Network Rail carrying out repair works on the bridge, structural examinations and vegetation works
  • HS2/SCS installing utilities trenches to allow for the connection of a water supply for the tunnel boring
    machines
  • HS2/SCS carrying out patch repairs to potholes around the
    Chiltern Bridge and HS2 site entrance

Access will be maintained for residents.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]