Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon, London
- Location
- Breakspear Road South
- Contractor
- SCS JV
- Type of works
- Bridge protection works, Utility works / surveys
- Estimated Start Date
- 01/04/2023
- Estimated End Date
- 16/04/2023
What we are doing
From 1 to 16 April 2023, we will be carrying out works along Breakspear Road South, north and south of the Network Rail
bridge. For safety reasons, a road closure will be in place for the duration of these works. These works include:
- Network Rail carrying out repair works on the bridge, structural examinations and vegetation works
- HS2/SCS installing utilities trenches to allow for the connection of a water supply for the tunnel boring
machines - HS2/SCS carrying out patch repairs to potholes around the
Chiltern Bridge and HS2 site entrance
Access will be maintained for residents.