Breakspear Road South road closure
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-06/03/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon, London
- Location
- Breakspear Road South
- Contractor
- SCS JV
- Type of works
- Culvert installation, Road closure
- Estimated Start Date
- 05/04/2025
- Estimated End Date
- 27/04/2025
What we are doing
From 5 to 27 April 2025, we will be carrying out works on Breakspear Road South, under a full 24-hour road closure north and south of the Network Rail bridge.
During the road closure we will:
- Remove and replace the culvert, including excavating a trench across the road to install the new drainage pipes
- Cut sheet piles along the area of the HS2 Breakspear Road bridge
- Install ditches by excavating and by clearing some vegetation and trees
The following traffic management will be in place:
- A full road closure will in place to ensure that the work can be carried out safely.
- A clearly signposted diversion route will be in place via Swakeleys Road B467/ High Road B466/ Ickenham Road/ High Street/ Bury Street A4180/ Breakspear Road.
- Local access to residential properties will be maintained, however, there will be no through access for emergency services.
- Two weeks of the closure will be within the Easter school holiday from 7 to 21 April 2025.
We would like to apologise for any disruption or inconvenience these works may cause.
For further details please follow the link to the notification below.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]