Bromford Drive footpath closure, Washwood Heath
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-50-26/09/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Washwood Heath
- Contractor
- BBV JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 23/10/2023
- Estimated End Date
- 01/12/2023
What we are doing
To construct the railway, we need to carry out utility diversions along Bromford Drive. To carry out these utility diversions safely, we need to manage pedestrians in the area. We will therefore be closing approximately 25 metres of the footpath along Bromford Drive from Monday 23 October to Friday 1 December 2023. During this time a diversion route will be in place for pedestrians.
The Bromford Drive carriageway will remain open.