View route map
BT Openreach cable installation at North Gower Street
Work item: HS2-MW-SCS-Ph1-Eu-St-S3-UT-24-22/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Drummond Street, Euston Road, North Gower Street
- Contractor
- CS JV
- Type of works
- Cable works
- Estimated Start Date
- 15/08/2022
- Estimated End Date
- 14/12/2022
What we are doing
Cable installation at the junctions with Drummond Street and Euston Road – August and September 2022 (night time works)
During August and September BT Openreach will be installing new cables and jointing these cables to the existing network. These works will take place at night and will not involve noisy working. There will be no excavation. All works will take place via existing BT chambers and manholes. Lane closures will be in place at these locations with traffic still able to access these roads. There will be no disruption to existing supplies during these works.