Cable diversion works and weekend works at Mandeville Road Vent Shaft site

Work item: HS2-SCS-25-1467

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road worksite
Contractor
SCS JV
Type of works
Cable works, Concrete break out, Excavation works
Estimated Start Date
12/11/2025
Estimated End Date
26/11/2025

What we are doing

From 12 November to 26 November 2025 we will be diverting the power cables to the Mandeville Road Vent Shaft site. This is in preparation for future works which will take place on Badminton Close.

We will be working on the railway embankments to the east and west of the site. The work will include ground excavation and breaking concrete, using an excavator and handheld tools.

Over the weekends 15/16 November and 22/23 November 2025 we will be working at the site entrance from 8am to 6pm. We will dig a trial hole, to locate existing cables.
On 4 and 5 November we will trim and clear low-level vegetation in the railway embankment.

Download information relating to these works