Monitoring works in Camden Cutting North

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-16/12/2022

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden Cutting worksite, Mornington Street Bridge, Park Village East, Parkway
Worksite Name
Camden Cutting
Contractor
SCS JV
Type of works
Construction, Piling, Traffic management, Utility works / surveys
Estimated Start Date
02/07/2018
Estimated End Date
28/12/2029

What we are doing

Ongoing monitoring in and around the Euston Approaches 

  • In September 2020, we installed prisms and reflectors on buildings and structures around the Euston Approaches, and installed ground studs on local footways.
  • The surveyors visit these locations each week to monitor ground movement in the area around our worksite to make sure movement is within safe limits.
  • We will continue to carry out these surveys until the project is complete.

Ground water surveys within the Park Village East carriageway

  • We take regular samples of the ground water from the boreholes on Park Village East to monitor and assess the impact of our works as we progress.
  • The boreholes are located within the carriageway, often next to parking
  • We may use traffic management to protect our working area while we carry out the surveys, these usually take about half an hour to complete bays.

Further details for above works please see notifications below.