CCTV and trial hole surveys on Greenford Road and Rockware Avenue

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-2-15/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Greenford Road, Rockware Avenue
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
10/10/2022
Estimated End Date
05/11/2022

What we are doing

What we are doing
From 10 October to 5 November 2022, we will be carrying out CCTV and trial hole surveys on Greenford Road and Rockware Avenue. The surveys will be conducted in three phases, in the areas shown on the map overleaf.

We will be digging trial holes, undertaking ground penetrating radar (GPR) surveys, and investigating the condition of the gas main on Greenford Road and Rockware Avenue.

Our survey team will be working within the carriageway under the bridge utilising a lane and footpath closure, to ensure the works can be carried out safely.

Your utility services will not be affected.

How these works might affect you
Temporary traffic management of a lane and footpath closure will be in place on Greenford Road and Rockware Avenue.

There will be intermittent noise whilst the road surface is being broken. We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.

We will ensure that disruption is kept to a minimum.

Phase of works
• Phase one: from 10 to 22 October, trial hole and gas CCTV Surveys between 8am and 5pm on footpath and carriageway
• Phase two: from 24 – 29 October, trial hole surveys on footpath and carriageway between 8pm and 5am
• Phase three: from 32 October to 5 November, trial hole survey between 8am and 5pm

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]