CCTV surveys on Bideford Avenue, Perivale
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-19/02/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Bideford Avenue
- Contractor
- SCS JV
- Type of works
- Survey
- Estimated Start Date
- 27/02/2025
- Estimated End Date
- 28/02/2025
What we are doing
We will be carrying out CCTV surveys on Bideford Avenue and Perivale Station Car Park on Thursday 27 and Friday 28 February between 8am and 4pm.
We will need to access the sewer under the ground through a manhole in the road and insert a camera to survey the condition of the sewer. We may need to wash the sewer with a jet washing machine to improve visibility for the camera.
There will be a short lane closure under the railway bridge on Bideford Avenue. We’ll install temporary traffic lights, a footpath closure and a pedestrian diversion. You may hear some noise if we need to jet wash the sewer. We will use noise reducing barriers where possible.
We apologise for any disruption these works may cause.