Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Eversholt Street
- Contractor
- Mace Dragados JV
- Type of works
- CCTV gas works
- Estimated Start Date
- 10/03/2025
- Estimated End Date
- 30/04/2025
What we are doing
CCTV investigative gas works – 10 March to late April 2025
As part of our essential utilities programme, we will be conducting CCTV investigative works on Eversholt Street. These investigations will help determine the future programme for the new gas main connection and other utility works in the area.
These works will commence on Monday 10th March 2025 and is anticipated to be completed in late April 2025. Working hours will be Monday to Friday, 8am to 5pm.
Works will be undertaken in two phases on northbound lane between Lancing Street and Drummond Crescent. During phase one of the works bus stop A will be suspended, and during phase two of the works bus stop B will be suspended and private hire vehicles will not be permitted to drop off or pick up passengers around our site on Eversholt Street. Please visit www.tfl.gov.uk for alternative stops and routes.
Both phases of works will require a northbound lane reduction with vehicular traffic being controlled by temporary traffic lights. Pedestrian access and safe crossing points will be maintained throughout the duration of these works.
For further details and location map please follow the link to the notification below.