Change of date for Public Right of Way (PRoW) W158 closure and diversion
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Prog-works-12-28/04/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Birmingham Road
- Worksite Name
- B4115
- Contractor
- BBV JV
- Type of works
- Works affecting Public Rights of Way
- Estimated Start Date
- 08/09/2025
- Estimated End Date
- 06/10/2025
What we are doing
Balfour Beatty VINCI (BBV) is working in partnership with HS2 Ltd to build the new railway.
To ensure the safety of the public, while we progress the construction of the railway and the realignment of Ashow Road, we will temporarily close footpath W158 and divert users to PRoW W157 .
We recently communicated that these works would take place from Monday 18 August to Sunday 14 September 2025. These dates have changed and we will now install the temporary closure of the PRoW from Monday 8 September 2025 to Monday 6 October 2025