Change to end date at Mandeville Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-25/03/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 15/04/2025
- Estimated End Date
- 31/08/2027
What we are doing
The end date for our works at the Mandeville Road Headhouse and Vent Shaft site has moved from summer 2026 to summer 2027.
We need to carry out works to connect the shaft to the tunnels by removing a concrete slab at the bottom of the shaft. The dates for these works have changed due to coordination with other ongoing works along the tunnel route. There has also been an unexpected change to the headhouse construction method.