Change to end date at Mandeville Road site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-25/03/2025

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, London
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Construction
Estimated Start Date
15/04/2025
Estimated End Date
31/08/2027

What we are doing

The end date for our works at the Mandeville Road Headhouse and Vent Shaft site has moved from summer 2026 to summer 2027.

We need to carry out works to connect the shaft to the tunnels by removing a concrete slab at the bottom of the shaft. The dates for these works have changed due to coordination with other ongoing works along the tunnel route. There has also been an unexpected change to the headhouse construction method.