Colne Valley Viaduct construction movements over Moorhall Road, Hillingdon

Work item: HS2-MW-Align-Ph1-Ar-Ce-C2-Prog-works-06/11/23

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Hillingdon
Worksite Name
Moorhall Road
Contractor
Align JV
Type of works
Plant crossing
Estimated Start Date
06/11/2023
Estimated End Date
10/11/2023

What we are doing

The launching girder being used to construct the Colne Valley Viaduct, named “Dominique”, will soon mark the halfway point in the construction of Britain’s longest viaduct by crossing over Moorhall Road in Hillingdon. Work to move the launching girder is expected to begin on Monday 6 November. Road traffic and pedestrians will not be affected by the works.

Work to transfer the launching girder over the pre-constructed deck over Moorhall Road will be undertaken from 6 November to 10 November 24 hours a day, subject to weather conditions.