Update: Concrete breaking at Mandeville Road Vent Shaft

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-17/02/2025_1

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Concrete break out
Estimated Start Date
31/03/2025
Estimated End Date
16/05/2025

What we are doing

Update: Below works planned from 10 March to 9 May were postponed to 31 March to 16 May 2025.

From 31 March to 16 May 2025 we will be breaking concrete near the main shaft at the Mandeville Road Vent Shaft site. This work is to prepare for building the headhouse base slab.

Handheld tools will be used to cut up the concrete surface and a vacuum excavator will then be used to break up the remainder of the concrete. You may experience increased noise and vibration during these works. Noise and vibration monitoring will be in place. We will use noise reducing barriers and water sprays to reduce dust.

We would like to apologise for any disruption this work may cause.

For further details please find the link to the notification below.

Download information relating to these works