Update: Concrete breaking at Mandeville Road Vent Shaft
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-17/02/2025_1
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Concrete break out
- Estimated Start Date
- 31/03/2025
- Estimated End Date
- 16/05/2025
What we are doing
Update: Below works planned from 10 March to 9 May were postponed to 31 March to 16 May 2025.
From 31 March to 16 May 2025 we will be breaking concrete near the main shaft at the Mandeville Road Vent Shaft site. This work is to prepare for building the headhouse base slab.
Handheld tools will be used to cut up the concrete surface and a vacuum excavator will then be used to break up the remainder of the concrete. You may experience increased noise and vibration during these works. Noise and vibration monitoring will be in place. We will use noise reducing barriers and water sprays to reduce dust.
We would like to apologise for any disruption this work may cause.
For further details please find the link to the notification below.