Concrete breaking out works in the satellite shaft, Mandeville Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-2-25/07/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Concrete break out
Estimated Start Date
05/08/2024
Estimated End Date
13/09/2024

What we are doing

From Monday 5 August to Friday 13 September 2024, we will remove a one-metre-deep concrete slab from the bottom of the satellite shaft. The dates for these works may change depending on progress of the tunnel boring machine.

These works will be carried out using high-pressure water jet machinery, petrol saws and excavators. We will use noise reducing barriers to help keep noise to a minimum. We will work as efficiently as possible, while keeping our work areas safe and tidy.

We would like to apologise for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.