Updated notice regarding concrete pour works, Water Orton

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-50-04/08/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Water Orton
Contractor
BBV JV
Type of works
Cement pours
Estimated Start Date
04/08/2023
Estimated End Date
05/08/2023

What we are doing

Updated notice

Revised dates

These works were due to be completed on Friday 11 August. However, due to reprogramming of the works, this will now take place on Friday 18 August from 7.00pm until an estimated time of 6.00pm on Saturday 19 August. As part of this work, we will deliver concrete to our site overnight from 7.00pm on Friday evening until Saturday morning at 8.00am. Our deliveries will enter site via Watton Lane for this time period. Then from 8.00am on Saturday morning all deliveries will enter our site via the M42 M6 link road access. Throughout the duration of the works, all deliveries will exit site via the M42 M6 link road access.

 

These works were due to be completed on Friday 4 August. However, due to reprogramming of the works, this will now take place on Friday 11 August from 7.00pm until an estimated time of 6.00pm on Saturday 12 August. As part of this work, we will deliver concrete to our site overnight from 7.00pm on Friday evening until Saturday morning at 8.00am. Our deliveries will enter site via Watton Lane for this time period. Then from 8.00am on Saturday morning all deliveries will enter our site via the M42 M6 link road access. Throughout the duration of the works, all deliveries will exit site via the M42 M6 link road access.

Water Orton Viaducts, that will carry the HS2 railway over the M42 M6 Toll, we will complete another concrete pour for pile caps at our compound on Watton Lane. (Location shown on the map in notification). A pile cap is a concrete mat that is laid above the piles to provide a stable foundation for us to build the structure.

This work will be completed from Friday 4 August from 7.00pm until an estimated time of 6.00pm on Saturday 5 August. As part of this work we will deliver concrete to our site overnight from 7.00pm on Friday evening until Saturday morning at 8.00am. Our deliveries will enter site via Watton Lane for this time period. Then from 8.00am on Saturday morning all deliveries will enter our site via the M42 M6 link road access. Throughout the duration of the works, all deliveries will exit site via the M42 M6 link road access.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]