Update on concrete pours at Mandeville Road Ventilation Shaft Site

Work item: HS2-MW-SCS-Ph1-Ar-So-S1-Ex-Mat-29-18/02/2024_02

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Concrete pours
Estimated Start Date
08/03/2024
Estimated End Date
29/04/2024

What we are doing

We wrote to you on 20 February 2024, to let you know that deliveries to Mandeville Road Ventilation Shaft site, will occur more regularly to enable continuous concrete pours into the main and satellite shafts.

The dates have been updated and for March concrete pours will take place on 8, 11, 12, 14, 26 and 28. April pours will take place on 2, 4, 6, 8, 10 and 29. We will update you if these dates change.
We expect these pours to be between 6am and 6pm. The concrete pours must be uninterrupted in order to maintain the structural integrity of the ventilation shaft walls.

There will be a delivery of machinery between 4am and 5am each day, ready for a 6am start. The machinery will be removed once the concrete pour is complete, which we estimate to be between 6pm and 8pm. We will close Mandeville Road, so that we can reverse a lorry out of the site to remove the machinery.

While on-site work is not expected to cause additional disruption, more delivery vehicles will be present due to the quantity of concrete that is required. Traffic Marshals will guide delivery vehicles as usual. Noise and vibration monitoring will continue, with extra noise suppression if needed.

We would like to apologise for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.