Construction of accommodation South Portal, West Hyde

Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Prog-works-30-29/01/2021

Work Item Summary

Project Phase
Phase 1
Region
Hertfordshire
Location
West Hyde
Contractor
Align JV
Type of works
Construction
Estimated Start Date
01/03/2021
Estimated End Date
30/04/2021

What we are doing

To facilitate our construction of the Chiltern Tunnel we will be erecting temporary overnight cabins for the duration of the works. These cabins will house staff overnight on the site. Works to install the block will begin in March and take until late April to complete.