Conveyor removal, Victoria Road, North Acton

Work item: HS2-SCS-25-1161

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Victoria Road
Worksite Name
Flat Iron site
Contractor
SCS JV
Type of works
Conveyor removal
Estimated Start Date
02/08/2025
Estimated End Date
11/10/2025

What we are doing

From 2 August to 1 November 2025, we will be working 24 hours a day, seven days a week to remove sections of the conveyor within the Flat Iron site and next to Dudding Hill Line bridge on Victoria Road, North Acton.

The conveyor, which has been used for transporting excavated material from the Northolt Tunnel excavation work, is no longer needed as the work is now completed.

You may notice noise from construction machinery and tools. Noisier works will be carried out during the day. We will use noise reducing barriers where possible. We will use floodlighting and direct the lighting away from local properties.

For further details and schedule of works please see the notification below.

Download information relating to these works