Cross passage construction near Alperton Lane

Work item: HS2-EW-SCS-Ph1-Ar-So-S1 -Tun-1-14/03/2025

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Alperton Lane
Contractor
SCS JV
Type of works
Cross passage construction
Estimated Start Date
31/03/2025
Estimated End Date
21/04/2025

What we are doing

From 31 March to 21 April 2025, we’re building a cross passage 9 between the newly built tunnels near May Gardens and Alperton Lane.

We’ll work 24 hours, seven days a week. To avoid overnight disturbance, we’ll limit noisy activities to between 7am and 10pm Monday to Sunday and carry out quieter works at night.

The cross passages will be built between the tunnels which will allow HS2 passengers to get to a place of safety in an emergency. They are located approximately 500 metres apart along the tunnels route.

This cross passage 9 will be about 20 metres below ground and 50 metres away from the closest property.