Update: Cross passage construction near Carr Road, Northolt
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Tun -1-20/01/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Carr Road
- Worksite Name
- Mandeville Road worksite
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 07/02/2025
- Estimated End Date
- 23/03/2025
What we are doing
Update: The works to build cross passage 19 near Carr Road, Northolt are extended until 23 March 2025 due to additional tunnel preparation requirements.
From 7 February to 23 March 2025, we will be constructing cross passage 19 below the ground, near Carr Road, Northolt.
We’ll work 24 hours a day, seven days a week. During this time there will be periods of noisy works. To avoid overnight disturbance, we’ll limit noisy activities to between 7am and 10pm Monday to Friday, 7am to 6pm on Saturday and 10 am to 3pm on Sunday and carry out quieter works during the night.
Cross passages between the tunnels will allow HS2 passengers to get to a place of safety in an emergency, and are approximately 500 metres apart along the route.
Cross passage construction involves breaking into the side of the completed tunnel. This might generate some noise and vibration which may be heard or felt as ground borne noise in nearby buildings when transmitted through the ground to the surface.
This cross passage is about 21 metres below ground and 30 metres away from the closest property.