Cross passage construction near Woodhouse Avenue, Perivale

Work item: HS2-EW-SCS-Ph1-Ar-So-S1 -Tun-1-27/05/2025

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Perivale
Contractor
SCS JV
Type of works
Cross passage construction
Estimated Start Date
19/06/2025
Estimated End Date
10/07/2025

What we are doing

From 19 June to 10 July 2025, we will be building cross passage 13 near Woodhouse Avenue, Perivale.

We’re building cross passages between the railway tunnels to allow HS2 passengers to get to a place of safety in an emergency. They are about every 500 metres on the tunnels route.

To build the cross passage, we will break into the side of the completed tunnel. This might cause some noise and vibration, which may be heard or felt as ground borne noise in nearby buildings. We’ll work 24 hours, seven days a week. To avoid overnight disturbance, we’ll limit noisy activities to between 7am to 10pm Monday to Sunday and carry out quieter works at night.

Cross passage 13 is about 20 metres below ground and lies within a thick layer of London clay, which will reduce noise and vibration during these works.

Download information relating to these works