Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden
- Worksite Name
- Euston Station
- Contractor
- Mace Dragados JV
- Type of works
- Decommissioning works
- Estimated Start Date
- 19/07/2024
- Estimated End Date
- 30/08/2024
What we are doing
Euston Station Canopy
From mid-July until late August 2024 we will install a temporary canopy in the station piazza. Most of the works will take place at night 10pm until 5am with minimum traffic management. Pedestrian access maintained throughout.
Euston Square Gardens – West
The decommissioning and construction of meanwhile green space is underway until end of August in Euston Square Gardens. The green space expected to be opened between September – October 2024.