Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Camden
- Contractor
- Network Rail (Euston)
- Type of works
- Maintenance work, Railway systems
- Estimated Start Date
- 04/03/2022
- Estimated End Date
- 11/03/2022
What we are doing
Overnight Work Near You
Overnight work will be taking place near you during the week of Friday 4 March – Friday 11 March 2022.
We need to remove the diesel from our tanks at Euston station. A tanker will enter the station off Eversholt Street and park within the station building. We will then extract the oil from the tanks using a pump mounted to the tanker and leave before the station opens. There will be one truck entering the station per night between the hours of 20.00-05.00. If any of our plans change, we’ll advise you via this website.
We do not expect our work to cause any disruption but wanted to keep you updated.
If you have any questions or concerns, please email [email protected] or call our 24-hr national helpline on 03457 11 41 41.