Diversion of footpath at Grand Union Canal, Harefield
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Traf-6-11/02/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Harefield
- Worksite Name
- Grand Union Canal
- Contractor
- Align JV
- Type of works
- Construction, Earth works, Vegetation clearance
- Estimated Start Date
- 23/03/2022
- Estimated End Date
- 29/04/2022
What we are doing
To enable the construction of one of the piers of the Colne Valley Viaduct we will install a welfare unit and small working compound next to the Grand Union Canal south of Harefield Marina. We will remove some vegetation from the south bank of the canal and build a temporary spur to the existing path to re-route users around the planned pier construction site. These works will take place during core working hours Monday to Friday 8am-6pm, and Saturday 8am-1pm in late March for 2-5 weeks.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]