Ecology works Fleet Marston
Work item: HS2-EW-Fusion-Ph1-Ar-Ce-C2-CR-7-03/04/2021 FUS_NL_0020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Aylesbury
- Contractor
- Fusion JV
- Type of works
- Environmental mitigation works, Fencing, Vegetation clearance
- Estimated Start Date
- 23/03/2021
- Estimated End Date
- 31/12/2021
What we are doing
In preparation for the main construction works we have built a number of new habitat sites along the HS2 route that will be populated not just by protected species, but also by a naturally diverse range of plants and animals. Ecological surveys have been completed in relation to species such as great crested newts, reptiles, badgers, owls and bats.
Following on from these surveys we will continue to carry out the seasonal mitigation works for species such as great crested newts and reptiles from the spring until the end of summer 2021. We will now be undertaking these works during 2021:
- ecology translocation
- ecology site maintenance
- fencing
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]