EKFB Working hours update – Radbourne to Southam
Work item: HS2 MW EK Ph1 Ar Ce C2 CR 04 05/05/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire, Warwickshire
- Location
- A423, Radbourne, Southam
- Worksite Name
- A423
- Contractor
- EKFB JV
- Type of works
- Extended working hours
- Estimated Start Date
- 13/04/2023
- Estimated End Date
- 31/10/2023
What we are doing
Notification of extended working hours by EKFB from Radbourne to Southam until the end of October 2023. The HS2 Code of Construction Practice (CoCP) provides details about the working hours that contractors are able to operate in. There are circumstances where ‘additional working hours’ will be required with the consent of the local authority.